Construction Look-Ahead for the Noerh Washington St. Bridge through July 8 is as follows:
Scheduled Work
• Installation of concrete deck placements
• Installation of bridge deck formwork
• Installation of bridge barrier and sidewalk formwork
• Cutover of utilities to permanent bridge
Work Hours
• Most work will be done during weekday daytime hours (6:00 a.m. – 4:00 p.m.)
Travel Tips
For everyone using the temporary bridge, please help share the space: walk to the right, walk bikes, and be mindful of people coming from both directions, if walking in a large group.
Drivers should take care to pay attention to all signage and move carefully through the work zone. Police details, lane markings, temporary barriers, traffic cones, signage, and other tools will be used to control traffic and create safe work zones.
The Tudor Wharf Walkway (under the bridge next to the water in Paul Revere Park) will be intermittently closed for safety during construction operations, with access provided via the Water Street underpass. The Boston Harborwalk under the bridge and eastern/harborside bridge sidewalk remain closed until rebuilt.
The contractor is coordinating with the TD Garden and local police to provide awareness and manage traffic impacts during events. For your awareness, the following TD Garden events are scheduled during this look-ahead period:
• Other Events: 7/7 at 7:00 p.m. and 7/8 at 7:30 p.m.
How can I find more information?
Stay up-to-date and informed by following the @MassDOT twitter account and Mass 511 for real-time updates, visiting the project website, or emailing us with any questions.
You can also sign up to receive project updates via email by clicking this link.
Project website: Mass.gov/north-washington-street-bridge-replacement Project email: [email protected]