The Construction Look-Ahead for the North Washington St. Bridge through May 13 is as follows:
Scheduled Work
• Installation of concrete deck placements
• Installation of bridge deck formwork
• Installation of electrical utility conduits on bridge structure
• Installation of gas and water utilities on bridge structure
Work Hours
• Most work will be done during weekday daytime hours (6:00 a.m. – 4:00 p.m.)
Contraflow Pilot
• The MassDOT-implemented contraflow pilot will continue to be in effect during evening peak traffic (3:00 p.m. to 7:00 p.m.), Monday through Friday.
• Police details, lane markings, temporary barriers, traffic cones, signage, and other tools will be used to control traffic during set up and operation of the contraflow.
Travel Tips
For everyone using the temporary bridge, please help share the space: walk to the right, walk bikes, and be mindful of people coming from both directions, if walking in a large group.
Drivers should take care to pay attention to all signage and move carefully through the work zone. Police details, lane markings, temporary barriers, traffic cones, signage, and other tools will be used to control traffic and create safe work zones.
The Tudor Wharf Walkway (under the bridge next to the water in Paul Revere Park) will be intermittently closed for safety during construction operations, with access provided via the Water Street underpass. The Boston Harborwalk under the bridge and eastern/harborside bridge sidewalk remain closed until rebuilt.
The contractor is coordinating with the TD Garden and local police to provide awareness and manage traffic impacts during events. For your awareness, the following TD Garden events are scheduled during this look-ahead period:
• CELTICS: May 9 time to be announced, and May 14 time to be announced.