Callahan Tunnel Project Update

The work schedule for the first two weeks of the Callahan Tunnel Project.  Work will happen 24 hours a day 7 days a week.  This schedule may change as work progresses.  An updated will be provided as needed.  Other concurrent activities may take place in conjunction with this work as needed.

Week of 28DEC-JAN04:

Mill Hot Mix Asphalt pavement and concrete topping slab

Demolish curb in tunnel at approaches

Work near the portals in the North End and East Boston ends of the tunnel will be on Saturday December 28th starting at 7am

 Week of JAN04-JAN11:

Begin demolition of concrete deck

Demolish curb in tunnel continues