Construction Update: North Washington Street Bridge Construction Look-Ahead Through May 29

This is a brief overview of construction operations and impacts for the North Washington Street Bridge Replacement Project. MassDOT will provide additional notices as needed for high-impact work and changes to traffic configurations beyond those described below.

Description of Scheduled Work 

•Building the piers:

*Pier 1 (closest to the North End): Column rebar installation and concrete placement.

*Pier 2: Column rebar installation and concrete placement.

*Pier 3: V-arms formwork.

*Pier 4: V-arms formwork, rebar installation, and concrete placement.

*Pier 5 (closest to Charlestown): V-arms formwork, rebar installation, and concrete placement.

•Installing, moving, and maintaining silt curtains in the water.

•Installing permanent fender piles

Work Hours

•Most work will be done during the daytime (6:00 a.m. – 6:00 p.m.)

Work That Has Been Completed

•Prior to 5/16:

*Pier 1 (closest to the North End): Mass-footing rebar installation.

*Pier 2: Mass-footing rebar installation.

*Pier 3: Curing column

Travel Tips

The Westerly sidewalk, Lovejoy Wharf stairs, near Converse are open to the public with the opening of the temporary bridge, the adjacent section of the Harborwalk passing under the bridge remains closed.

The Tudor Wharf Walkway (under the bridge next to the water in Paul Revere Park) will be intermittently closed for safety during construction operations, with access provided via the Water Street underpass.